Jan De Messemaeker said:
Hi Tom,
Your option to split must be on, and what you see (and do not like) is
what
I thought you needed.
Actually, I assumed it was on (and it is).
I actually do like it as I said after looking at it.
And sorry,, the option is in Tools, Options, schedule instead of
Calculation... I always mess up those two.
I would never be able to remember where all the options are myself.
I'm glad you are finding a process you like, but I'm still at a complete
loss here.
What's the point of registering a % complete if afterwards you move that
anyway?
I also put it back to done. It is just that I don't care about the when it
was started. Just what the status is. How much of it is done.
The split does what I want - as you rightly said. What was happening before
SP2, and what started the whole problem, was that if I added a task or
changed a duration before a task that was started - all the start dates
would be wrong because the dates of all the tasks that followed a task that
was started was based on that task. If that task didn't change - than none
of the tasks after it would change. Now that is not the case. It may be
that I didn't have the split on or maybe it wasn't available (not sure).
It is done - just that I wanted the graph to show it inline with the other
tasks. Even though each task depended on the task before it (in my case), I
will not necessarily work on it in that order (as would not happen if you
have a team working on different tasks at the same time).
I like a tool that at least tries to simulate reality not just a set of
calculation rules I make up, sorry.
And in my world done is done, shouldn't move any more.
But that was my point. It isn't reality. The actual start date that gets
fixed is not the current date - but the date that the system calculated when
the project was built. As I mentioned in my last post, the date on the task
I was setting as started had a start date of 3/14/07. The date it should
have had for a start date would be the current date (3/2/07). That is
reality. If you look at the graph it looks like the task was started 2
weeks from now. That isn't reality, is it?
No difference from moving it. The status of the job is still started or
finished (that doesn't change) just the date, which is ambiguous anyway.
Now if you actually modify the date to the correct date or use the Resource
Usage sheet (which sets the actual start date to the current date, I think),
then that would be more like reality.
In my case, I also might set the task as started or finished a week after it
is done which would have the wrong date also (and I probably wouldn't
remember exactly which date I started on anyway).
About fixing the start date where it was.
How can project know the start date was any other date if you don't tell
it?
I agree. But I am just putting the %Completed from the Gnatt Chart and not
opening the Task Information screen to input the percent complete. I would
have thought it might use the current date if you don't put it in - but it
doesn't. But again not important to me.
Try to think away from %complete (something I never never never enter), it
is the result of a calculation but it should not be the start of one as it
leaves all questions about the work done open: Project fills them with
defaults but those are only defaults. And the default for actual start is
the planned start..; I fail to see what would be a better default.
And for someone who doesn't stop repeating dates are not important, you
put
quite a lot of attention to Actual start.
No. I was just making a point about reality. And if you are putting the
actual start date manually or allowing the system to put the date in from
the Resource Usage sheet then my point doesn't really apply. I was going by
my case where I am just change the %Completed and the system is using an
amiguous date (which is not important to me as you say). As I say and you
say I say (that's a lot of says) the date isn't import, which is why I
wouldn't put the Actual Start Date in.
Indeed, I personally attach a lot of attention to dates (as does your boss
if I understand you right) but ONLY dates in the future. That is why I
like
the way Project has with those split tasks...
Actually, he isn't concerned with dates just the status of the tasks. In my
case, I am working on different projects which change priority all the time,
so the dates a particular task is started is not important.
Thanks,
Tom