Hi,
I am allocating two people to a task. (lets say the task is 8 hours). Person
A is allocated 6 hours and Person B is allocatd 2 hours. How can i get
Project to show that as allocated hours in the line info on the Gannt chart,
and not as Person A with 75% or .75 and Person B with 25% or .25 (I would
like the result to be Person A= 6 Person B= 2)
Cheers