N
Nathan Jones
Hello.
My question relates to managing resources for tasks that can occur
simultaneously.
If I have 2 tasks being performed by the same person that I know will take
them 2h, but that both can be performed and completed in that time, what is
the best way to track the resource allocation?
Project allows only %time allocation to be calculated (it seems) and so if I
determine a %allocation of time basd upon the fixed duration and the number
of tasks I can't add another task without throwing out the calculation and
overallocating that person.
Can this be alleviated by autocalculating, or will this end up changing my
overall allocation of resources?
Many thanks for any suggestions.
My question relates to managing resources for tasks that can occur
simultaneously.
If I have 2 tasks being performed by the same person that I know will take
them 2h, but that both can be performed and completed in that time, what is
the best way to track the resource allocation?
Project allows only %time allocation to be calculated (it seems) and so if I
determine a %allocation of time basd upon the fixed duration and the number
of tasks I can't add another task without throwing out the calculation and
overallocating that person.
Can this be alleviated by autocalculating, or will this end up changing my
overall allocation of resources?
Many thanks for any suggestions.