M
mikejw
Hello,
I'm using MS Project 2003 Standard and have several tasks that are not
constrained, do not have a successor, have not started and finish well before
the "calculated" project finish date, yet these tasks show 0 slack. I think
the slack should show the days between their finish and the project finish.
These are not critical tasks. Do I have to link these tasks randomly
downstream?
Thanks for your assistance.
Mike W
I'm using MS Project 2003 Standard and have several tasks that are not
constrained, do not have a successor, have not started and finish well before
the "calculated" project finish date, yet these tasks show 0 slack. I think
the slack should show the days between their finish and the project finish.
These are not critical tasks. Do I have to link these tasks randomly
downstream?
Thanks for your assistance.
Mike W