Hi ,
is there a way to assign different resources to each individual piece of a
split schedule instead of to the whole sche...
for example, I have a schedule for 9 days in total..with 2 different
resources...I would like to be able to put resource 1 on the First
split task and then resource 1 & 2 on the Second split and resource 2 only
on the third. Is that possible...?
can't seem to find anything out.
appreciate your Help
thanks
Matt