Splitting a task

S

Sneha Satish

Hi All,

I have an activity in the project with a duration of 4 days. I have assigned
a resource for this activity. I have a successor for this activity. After
baselining the activities in the project, I need to split the predecessor
activity by 3 days and complete the successor activity and come back to the
predecessor activity. This should not cause any variance in the project. Can
you pls help me find a solution to the same.
 
G

Gérard Ducouret

Sneha,
Is the dependency bewteen the 2 tasks a FS link?
If in the real world you are able to do what you want, that means that this
FS link is false. Try to replace it by a SS link, plus x days. Then split
the predecessor as you want.
Gérard Ducouret
 
S

Sneha Satish

Hi Gerard,

I have tried the option by giving a SS+2days, completed the successor
activity and came back to predecessor and gave a split, it still shows me a
finish variance.
 
M

Mike Glen

Hi Sneha ,

Welcome to this Microsoft Project newsgroup :)

I think I would split the task into 2 separate tasks and re-link
accordingly as that is what you plan to do.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
S

Sneha Satish

Hi Mike,

Let me put it this way

I have two activities say a and b ; a being the predecessor and b being the
successor. I have the same resource working on both the activities. While the
resource is working on activity a, there is some work that needs to be done
on activity b and then he needs to come back to activity a. In this scenario,
can I split the task or is there another alternative
 
M

Mike Glen

Have you tried levelling? Put a high priority onto b and level
Priority,Standard, and allow splits.

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top