S
Sneha Satish
Hi All,
I have an activity in the project with a duration of 4 days. I have assigned
a resource for this activity. I have a successor for this activity. After
baselining the activities in the project, I need to split the predecessor
activity by 3 days and complete the successor activity and come back to the
predecessor activity. This should not cause any variance in the project. Can
you pls help me find a solution to the same.
I have an activity in the project with a duration of 4 days. I have assigned
a resource for this activity. I have a successor for this activity. After
baselining the activities in the project, I need to split the predecessor
activity by 3 days and complete the successor activity and come back to the
predecessor activity. This should not cause any variance in the project. Can
you pls help me find a solution to the same.