L
Lynette
I'm trying to figure out how to handle something. Our project has lots of
tasks and subtasks. I know the start/end dates for the task itself, but,
don't know all the start and end dates for the subtasks, just some. When I
don't know the start date, it defaults to the project start date. That's ok
for now. At this time, I don't have a subtask as late as what will be the
project end date. So, how do I get the task to start on the start and end
dates I want without having some tasks with the actual end date? Does that
make sense? I know I have 3 subtasks that end on 3/3/08 for instance, but,
eventually will have some that will end on 6/1/08, but, don't have any yet.
I can't get the task to display the 6/1/08 date though. It says the task
will end on 3/3/08.
If anyone could give me some ideas, I'd greatly appreciate this. This
project is for a large software development project.
tasks and subtasks. I know the start/end dates for the task itself, but,
don't know all the start and end dates for the subtasks, just some. When I
don't know the start date, it defaults to the project start date. That's ok
for now. At this time, I don't have a subtask as late as what will be the
project end date. So, how do I get the task to start on the start and end
dates I want without having some tasks with the actual end date? Does that
make sense? I know I have 3 subtasks that end on 3/3/08 for instance, but,
eventually will have some that will end on 6/1/08, but, don't have any yet.
I can't get the task to display the 6/1/08 date though. It says the task
will end on 3/3/08.
If anyone could give me some ideas, I'd greatly appreciate this. This
project is for a large software development project.