stretch a task between dates

L

Len

I have a project that has a fixed start and variable end dat. Is there a way
to have project "fill" a fixed work task between the start date and the end
milestone?
 
J

Jan De Messemaeker

Hi,

The link to the faqs is in my signature below.
Read FAQ 19: Hammock Tasks

HTH
 