H
Henk
Hi Project Experts,
I want to complete an analysis in which the amount of work on tasks in
a given daterange is calculated. When I apply the daterange filter,
the tasks from 1-jan-07 till 31-dec-07 are filtered correctly. However
the subtotals on the summary tasks show the amount of work for the
complete daterange of the projects!
e.g.
Summary Task 110h work
task 1 60h work start 1-oct-06 finish 1-dec-06
task 2 10h work start 1-feb-07 finish 1-apr-07
task 3 40h work start 1-may-07 finish 1-jul-07
When I apply the daterange filter for tasks in 2007, the summary task
still shows an amount of 110h work, where 50h was wanted, because
task1 in the example was completed in 2006.
Does anyone know how to solve this problem?
Best regards, Henk
I want to complete an analysis in which the amount of work on tasks in
a given daterange is calculated. When I apply the daterange filter,
the tasks from 1-jan-07 till 31-dec-07 are filtered correctly. However
the subtotals on the summary tasks show the amount of work for the
complete daterange of the projects!
e.g.
Summary Task 110h work
task 1 60h work start 1-oct-06 finish 1-dec-06
task 2 10h work start 1-feb-07 finish 1-apr-07
task 3 40h work start 1-may-07 finish 1-jul-07
When I apply the daterange filter for tasks in 2007, the summary task
still shows an amount of 110h work, where 50h was wanted, because
task1 in the example was completed in 2006.
Does anyone know how to solve this problem?
Best regards, Henk