V
VijoJoseph
Is it possible for MS project to calculate a task dependency both up and down
linked tasks. For this example, there are a few manufacturing steps which
are linked. They want to know what the impact on the schedule is if any of
the time of the tasks change.
Task A - 10 minutes
Task B - 20 minutes
Task C - 15 minutes
Task D - 5 minutes
If tasks A, B, C, and D are all linked, if C takes 30 minutes, can Project
calculate the impact both on A, B and D? I understand it can flow down to D.
Can it flow up to A & B?
linked tasks. For this example, there are a few manufacturing steps which
are linked. They want to know what the impact on the schedule is if any of
the time of the tasks change.
Task A - 10 minutes
Task B - 20 minutes
Task C - 15 minutes
Task D - 5 minutes
If tasks A, B, C, and D are all linked, if C takes 30 minutes, can Project
calculate the impact both on A, B and D? I understand it can flow down to D.
Can it flow up to A & B?