I have input certain tasks' durations in months (ex: 3 mons). However the
task duration in months results in months which seem to be shorter than
calendar months!! What do I need to do to make my task month duration be
equal to the calendar month duration? Thanks for help. Jiri
 
M

Mike Glen

Hi Jiri,

Welcome to this Microsoft Project newsgroup :)

You can't as months vary in length. Use days or weeks or, in
Tools/Options/Calendar, redefine a month from 20 working days to something
nearer your requirements.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
S

Steve House [Project MVP]

Remember that duration is defined as the amount of working time required to
complete a task. Time where no one is able to work to drive the task
forward doesn't count. While a calendar month may have 30 days, only about
20 of those days matter in terms of scheduling work.
 