J
Jim
Working on a project schedule, I have a task which has a predecessor. The
task is set to Finish to start. The predecessor task actual is a series of
sub tasks. The longest sub task finished early by several weeks and is
marked 100% complete but new task is still not changing its beginning start
time.
example: using current date of 6/14
Develop code
Pgm 1 start 6-1 finish 6-3 100% complete
pgm 2 start 6-3 finish 6-20 80 % complete
Pgm 3 start 6-7 finish 6-29 100% complete
system test (predecessor develop code)
test 1 start 6-29 finish 7-3 set as F-S
What do I need to do to have MS Project change the start date to 6-20 or
when ever pgm 2 finishes
task is set to Finish to start. The predecessor task actual is a series of
sub tasks. The longest sub task finished early by several weeks and is
marked 100% complete but new task is still not changing its beginning start
time.
example: using current date of 6/14
Develop code
Pgm 1 start 6-1 finish 6-3 100% complete
pgm 2 start 6-3 finish 6-20 80 % complete
Pgm 3 start 6-7 finish 6-29 100% complete
system test (predecessor develop code)
test 1 start 6-29 finish 7-3 set as F-S
What do I need to do to have MS Project change the start date to 6-20 or
when ever pgm 2 finishes