Task Name without Duration etc.

T

Tbugs

Hello and thank you in advance for helping me with my question.

I have been creating programmes using Microsoft Project which require the
Duration, Start and Finish dates to be displayed.

Is it possible to have a task name entered as a heading leaving all the
duration, start and finish dates blank somehow?

Thanks again,
T
 
J

JulieS

Hi Tbugs,

No, I'm afraid not. All tasks in Project will have a start and finish date
as well as a duration. You could change the font color of the start,
finish, and duration fields to white to "hide" them, but the data will still
be there, just not visible.

Hope this helps. Let us know how you get along.

Julie
 