G
G Lykos
Greetings! This is to check my understanding from observation of how task
splitting works. (1) It would appear that when a task is split, which can
only be done graphically, Project moves the work for the assigned resources
from the start of split out to the end of the split-off portion of the task
as you pull the split over. This achieves the same result as manually
zeroing out a resource's work in the middle of a task assignment and moving
it to the end. (2) Different than (for example) a delay, there is no
parameter to record a split point or duration. As a result, in order to
adjust a split, you must grab the task bar and move it, or fiddle with the
daily work assignments. Also, there isn't a parameter that can be tested to
check for a split.
Does this sound about right?
Thanks,
George
splitting works. (1) It would appear that when a task is split, which can
only be done graphically, Project moves the work for the assigned resources
from the start of split out to the end of the split-off portion of the task
as you pull the split over. This achieves the same result as manually
zeroing out a resource's work in the middle of a task assignment and moving
it to the end. (2) Different than (for example) a delay, there is no
parameter to record a split point or duration. As a result, in order to
adjust a split, you must grab the task bar and move it, or fiddle with the
daily work assignments. Also, there isn't a parameter that can be tested to
check for a split.
Does this sound about right?
Thanks,
George