A
Alfatcop
Hello,
I have a project constituted of individual tasks (fixed work) with typical
dependencies (Finish to start) and worshops (fixed duration) with all
resources attending those last. I have set a high priority on the workshops
and perform levelling (priority, standard) with the task split option ON.
MS Project does a good job in splitting the individual tasks for the
workshops to occur.
The problem I have is that MS project also split the individual tasks to
allow for the best resource allocation ....resulting in very splitted tasks.
The only way I have found is to set "start no earlier" constraints on this
individual tasks to avoid this excessive split ..I am not quite sure this is
the best way !!!
Hope I have been clear enough
Thanks for your help,
I have a project constituted of individual tasks (fixed work) with typical
dependencies (Finish to start) and worshops (fixed duration) with all
resources attending those last. I have set a high priority on the workshops
and perform levelling (priority, standard) with the task split option ON.
MS Project does a good job in splitting the individual tasks for the
workshops to occur.
The problem I have is that MS project also split the individual tasks to
allow for the best resource allocation ....resulting in very splitted tasks.
The only way I have found is to set "start no earlier" constraints on this
individual tasks to avoid this excessive split ..I am not quite sure this is
the best way !!!
Hope I have been clear enough
Thanks for your help,