Task will not split

M

Meredith

When I try to split a task, it extends instead of splitting. I have checked
to make sure the "Layout" box shows split task and also checked the Options
box to split in-progress tasks. Any other suggestions?
 
M

Mike Glen

Hi Meredith,

Welcome to this Microsoft Project newsgroup :)

How did you try to split the task? With the mouse? Or putting zeros in the
Task Usage view?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top