Shane
Hi there.
I've got a project scheduled and I've put in place calenders for different
resources. One particular resource has 21/10 and 22/10 as nondefault working
days.
I also have a task however, assigned to that resource which has a duration
of one day, a start of 20/10 but a finish of 23/10.
Does anyone know why project schedules in this way, and of any changes I can
make to this task finishes on 21/10, as it should?
Cheers
Shane