P
pegs
My setup is that I have many fairly small projects. The tasks are of short
duration 1-4 hours normally. If task #1 doesn't get started (For example it
was scheduled to start yesterday, I want the next task to be listed as
starting tommorrow not today as was originally scheduled. I won't necessarily
be opening that project or myslef even know that the task got started late,
but I don't want the next person in line thinking they have a task starting
today when the task above them didn't get done. I don't want it to show up in
their tasks. I have current projects set to 1 day.
I have set my dependencies up FS and added a day lag time. It doesn't seem
to recalculate until I enter something into the task above, but I want it to
keep moving the dates if it doesn't get started.
duration 1-4 hours normally. If task #1 doesn't get started (For example it
was scheduled to start yesterday, I want the next task to be listed as
starting tommorrow not today as was originally scheduled. I won't necessarily
be opening that project or myslef even know that the task got started late,
but I don't want the next person in line thinking they have a task starting
today when the task above them didn't get done. I don't want it to show up in
their tasks. I have current projects set to 1 day.
I have set my dependencies up FS and added a day lag time. It doesn't seem
to recalculate until I enter something into the task above, but I want it to
keep moving the dates if it doesn't get started.