Tasks that need to be completed each week

T

t_rooking1

For a particular project, I have a number of summary tasks running in
parallel.

What is the easiest way to see the tasks that need to be completed this
week?

How can I sort the tasks by start date, and is this the best way to see
the tasks that need to be completed each week?

Thanks for your help
 
R

Rod Gill

Hi,

Select Project, Filtered For, AutoFilter

Click the triangle in the Finish date column and select this week
 