Total cost with multiple resources for single task

T

Tim

When you assign multiple resources to a task with Fixed Work and the
resources have different rates such as Project Manager - $85 @ 25% and
General Contractor - $150 @ 50%, how Project calculate the cost?
 
D

Dale Howard [MVP]

Tim --

The software multiplies the Standard Rate for each resource by the hours of
Work assigned for each resource. It also multiples the Overtime Rate by the
Overtime Work for each resource. Finally, it adds the Fixed Cost for the
task. Then it totals this all up and calls it the Cost for the task. Hope
this helps.
 