I have several different one day projects that will be repeated periodically
in the future. What is the best way to get the task start times to come
forward to the new Project Start date, and each task have the original start
time. I can only get the tasks to all start at the beginning of the day - I
change the Project Start date, then (Select all tasks, Project>Task
Information>Change start date to new Project Start date - all tasks begin at
7:00 AM, the default.