using projects over

V

Vig

I have several different one day projects that will be repeated periodically
in the future. What is the best way to get the task start times to come
forward to the new Project Start date, and each task have the original start
time. I can only get the tasks to all start at the beginning of the day - I
change the Project Start date, then (Select all tasks, Project>Task
Information>Change start date to new Project Start date - all tasks begin at
7:00 AM, the default.
 
V

Vig

THanks Jan,

The gretat majority of task dates were adjusted; a minority were not. I will
do more testing to see if I can discover why.

Jan De Messemaeker said:
Hi,

Run adjust dates on the analysis toolbar
HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top