View tasks that are scheduled in current week

T

Tim Sheldrick

Using Project 2003, I want to create a view/filter that only shows the tasks
that have time scheduled against them in a specified time frame (e.g current
week).

I know that I can filter on start time and finish time, but if a task goes
over the time frame, I want to be able to include it in the view, but not
include tasks that are not scheduled for work in the time frame.
 
T

Tim Sheldrick

Hi and thankyou for taking the time,

Unfortunately the Date Range filter uses the Start and Finsih fields only to
determine which tasks span the time frame. It does not consider whether
there is any work actually scheduled within the week in question.

Any other thoughts?

Thanks in anticipation.
 