Weekends still show as non-working time

J

Joseph Bloch

I'm using Project Server 2002 and MS Project 2002. I've checked out
the Enterprise Global, created a new calendar, and set all days to
have working hours 9 AM - 11:59 PM.

The problem is, in the Gantt Chart view, Saturday and Sunday still
comes up as nonworking time.

How can I make Saturday and Sunday to be working days, if not by
setting them as such in the calendar?

Thanks,

Joseph Bloch
 
D

Dale Howard

Joseph --

By default, the Project calendar (Project - Project Information) and the
Nonworking Time calendar (Format - Timescale - Non-working time) are both
set to the Standard for new blank projects. This is why you are still
seeing Saturday and Sunday as nonworking time. If you begin with a blank
project, you will need to change both calendars to your new company calendar
manually. If you are using enteprise templates, you can set both of the
calendars in each template. Hope this helps.
 
S

Steve House

Right click on the timescale at the top of the Gantt chart, choose
Timescale from the menu, select the non-working time tab and there
designate the calendar that governs the display of the gray non-working
days bars or turn them off all together.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top