Hello Julie:
1. I created a resource pool with the three projects
2. I brought up hte resource usage view in the master resource file
and
added the project name (great)
3. I brought up the Resource Usage view and is showed the resource
usage by
project name.
4. However when trying to sort the view so all the tasks for a
given
resource displayed, it just sorted the view alphabetically by the
name
field
(contains the resource name and task name, instead of displayiing
the
Resource name and all tasks regardless of the project they belonged
to
under
that resource...
Is there a way to view the information by resource name (major),
followed by
each task assigned to that resource, regardless of the project it
came
from????
Thanks
Paul
P.S. Julie says hello
:
Hi aspkg,
My answers are embedded.
I'd like to be able to:
1. merge several projects using the same resources
[Julie] Yes, by using a resource pool file. Fellow MVP, Mike Glen
has
written an excellent series of articles on MS Project. His
articles
may
be found at:
http://project.mvps.org/mike's_tutorials.htm
Articles number 17 & 18 give great detailed information about how
to
create resource pool files.
2. print the who/what/when report which also shows the project,
because the
merged reports are from a standard template with the same task
names,
so i
have triple entries with no way to differentiate them to the
project
Can this be done?
[Julie] I'm afraid not directly. The Who Does What When report is
very
limited as to what additional data can be added to the report.
However,
the report is essentially the Resource Usage view. You can add
the
Project field to the table (left side) of the Resource Usage view
to
help differentiate what assignments are coming from what project
files.
Zoom the timescaled portion as needed and then print the view.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project