Thanks Glen. I have tried the 'obvious' already. But, thanks for your reply.
I actually figured out the solution. This is for summary tasks displaying
99% completion when their detailed tasks are 100% completed. This is the
result of having a resource at 0% on the summary tasks. The workaround is to
delete the resource from the summary task, then put it back.