why summary tasks show 99% completion

L

Lindabonita

why summary tasks show 99% completion when all of its detail task are 100%
completed.
 
M

Mike Glen

Hi Lindabonita ,

Welcome to this Microsoft Project newsgroup :)

I suspect you have a milestone or two which you haven't marked as 100%.
Filter for milestones and check %Complete field for them.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
L

Lindabonita

Thanks Glen. I have tried the 'obvious' already. But, thanks for your reply.
I actually figured out the solution. This is for summary tasks displaying
99% completion when their detailed tasks are 100% completed. This is the
result of having a resource at 0% on the summary tasks. The workaround is to
delete the resource from the summary task, then put it back.
 
M

Marcel Romahn

In general: by defining details for summary tasks, nobody will be able to
understand what project will calculate ;-) Never do thinks like that...
 