MS Project 2003 / using XP
I have two task both for 2hrs (normal 8hrs working day). I set the type to
fixed work and assign a resource to both tasks.
Project automatically places a percentage i.e 29% and the duration stays at
1 day. If I then change the resouce to 100 percent on both tasks. When I
view the resource graph its says the reource is over allocated??
Doesnt project work out the resource and hour usage to determine if the work
can be done in a day..
ie. if 1 resource is 100% allocated on 4 tasks, each with 2 hr work
estimate, doesn't that mean you are not over allocated for that day???
I'm working through the book Dynamic scheduling but cant seem to get my head
around this????
I have two task both for 2hrs (normal 8hrs working day). I set the type to
fixed work and assign a resource to both tasks.
Project automatically places a percentage i.e 29% and the duration stays at
1 day. If I then change the resouce to 100 percent on both tasks. When I
view the resource graph its says the reource is over allocated??
Doesnt project work out the resource and hour usage to determine if the work
can be done in a day..
ie. if 1 resource is 100% allocated on 4 tasks, each with 2 hr work
estimate, doesn't that mean you are not over allocated for that day???
I'm working through the book Dynamic scheduling but cant seem to get my head
around this????