Calendars

C

Caz

Hi
I work with MS2003 Project Enterprise. Can anyone tell me if I can set up a
calendar that runs inline with our fiancial reporting period, which doesn't
run to a calendar month. (The start and finish dates vary from month to
month) If this is possible does the resource view show this date range or
does the standard calendar month still show.,

caz2007
 
M

Mike Glen

Hi Caz,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top