Can a subsection of project tasks be moved keeping original start

J

JANP

Can a whole subsection of project tasks be moved while keeping the
relationship between all the tasks the same and keeping the original project
start date?
Using Microsoft Project Standard 2002
 
J

John

JANP said:
Can a whole subsection of project tasks be moved while keeping the
relationship between all the tasks the same and keeping the original project
start date?
Using Microsoft Project Standard 2002

Janp,
I guess it depends on what you mean by "move". If a group of tasks is
dragged and dropped within a given file, then links on those tasks will
be maintained. If on the other hand you are talking about copy and
pasting a group of tasks from one project to another, then the links
will not follow, new external links will need to be set up.

As far as the original project start date that won't change unless the
group of tasks are being copied and pasted from one file to another.
Depending on what your end goal is, you may need to set up a constraint.

John
Project MVP
 
J

Jan De Messemaeker

Hi,

Yes, but to advise you about the enbst way to approach this I would like
some more detail.
Move all incomplete tasks to start after acertain date? Tools, Tracking,
Update Project, Reschedule ...
Whet else?
HTH
 
J

JANP

Hi John,

Thank you for the quick reply. Yes, I would like to select a group of tasks
and move them forward by three weeks. I am a novice user and I am not sure
how to drag and drop the selected group of tasks from the Gantt chart view.
Should I be using another view to do this? Thank you kindly,

JanP
 
J

John

JANP said:
Hi John,

Thank you for the quick reply. Yes, I would like to select a group of tasks
and move them forward by three weeks. I am a novice user and I am not sure
how to drag and drop the selected group of tasks from the Gantt chart view.
Should I be using another view to do this? Thank you kindly,

JanP

JanP,
OK, it's not too hard but dragging and dropping and moving the schedule
out (tasks performed later) are two different things. I'll explain how
to do both.

To drag and drop a block of tasks to another location in the file use
this process. First, make sure drag and drop is enabled. Go to
Tools/Options/Edit tab. Make sure the "allow cell drag and drop" option
is checked. Then select the group of tasks you want to move. If the
first line of the group is a summary task you only need to select it -
the subtasks will go with it. Next place your mouse cursor over the ID
number in the extreme left hand column of the first selected row.
Holding the mouse button down, drag the group of tasks to where you want
it.

Slipping a group of tasks out depends on a couple things. If the tasks
are all linked (which they probably should be) it is much easier.
Otherwise you will need to move each task out independently. Normally
the start date of a task is determined by its link to a predecessor -
some other task that must finish before the that task can start.
However, in some cases a task (or group of tasks) is independent of
other tasks in the plan. In that case it is permissible to directly
enter a date in the Start field of the task(s). This will place a
constraint of "start-no-earlier-than" on that task. For a linked group
of tasks you only need to do this for the first task in the link chain
because the other tasks will simply respond to the links.

Hope this helps.
John
Project MVP
 
C

Concreteman

I believe you answered your own question... if your tasks are all
linked properly, you could add lag time for the first task you want to
move out 3 weeks and the rest will follow. You would create a
Finish/Start + 3 weeks... Unless I didn't read the question right. If
the task is the first one, either add one before it at the start, or
create a hard constraint (not recommended).
 
D

DavidC

One cautionary note I would add is to make sure that under
Tools/Options/Schedule, the field "Autolink new or moved tasks" is NOT
selected.

If this is selected and you do move tasks then they will automatically link
with adjactent tasks and potentially cause real havoc.

Regards

DavidC
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top