yomtov
I would like to have different levels for FS dependencies. For example;
certain tasks heve to start when the predecessor is 75% finished. Others when
the predecessor is 85% finished. Is there a way to do this in Project?
All help is appreciated.
certain tasks heve to start when the predecessor is 75% finished. Others when
the predecessor is 85% finished. Is there a way to do this in Project?
All help is appreciated.