Can I set the % of completion for a FS dependency?

Y

yomtov

I would like to have different levels for FS dependencies. For example;
certain tasks heve to start when the predecessor is 75% finished. Others when
the predecessor is 85% finished. Is there a way to do this in Project?

All help is appreciated.
 
D

Dale Howard [MVP]

yomtov --

Yes, you can do this. To show that the successor begins when the
predecessor is 75% completed, do the following:

1. Link the tasks with an FS dependency.
2. Double-click the link line between the tasks to open the Task Dependency
dialog.
3. Enter -25% in the Lag field.
4. Click the OK button.

NOTE: You must enter the percent symbol (%) with the negative number in the
Lag field. Hope this helps.
 
Y

yomtov

Thank you.

Dale Howard said:
yomtov --

Yes, you can do this. To show that the successor begins when the
predecessor is 75% completed, do the following:

1. Link the tasks with an FS dependency.
2. Double-click the link line between the tasks to open the Task Dependency
dialog.
3. Enter -25% in the Lag field.
4. Click the OK button.

NOTE: You must enter the percent symbol (%) with the negative number in the
Lag field. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top