S
SteveA
I am reviewing a project and trying to reduce the over allocation
present. In many cases I was able to identify a task as the only task
possible to work on(ie travel nec.) and was able to split another task
accordingly. Unfortunately, that won't work when a new task is
assigned and can be worked concurrently. How do I adjust the 100% to
50% mid task so that both tasks are worked without resource over
allocation?
Please ask if I can provide more information.
Thanks in Advance.
v/r
Steve A.
present. In many cases I was able to identify a task as the only task
possible to work on(ie travel nec.) and was able to split another task
accordingly. Unfortunately, that won't work when a new task is
assigned and can be worked concurrently. How do I adjust the 100% to
50% mid task so that both tasks are worked without resource over
allocation?
Please ask if I can provide more information.
Thanks in Advance.
v/r
Steve A.