C
Colleen
Hi, my group utilizes the information listed below for their weekly
reporting. However, they are doing this report manually by copying and
pasting from the project plan I send them into an Excel spreadsheet that has
formulas to calculate and get these results. Can you give me some tips on
custom reporting that can be automated in MS Project that would give me these
same results? It seems so manual how they are doing it now and it seems like
there must be a way to have this information in custom reports run directly
from the project plan. They have been doing this for years and no one seems
to use MS Project reports and I think there must be an easier way to automate
this. Thanks.
1) Baseline comparison calculation from Day 1-100 of project
i) 100 Day % Complete
ii) Baseline % Complete today
iii) Actual % complete today
iv) Variance
v) Work last week
vi) Actual Work
vii) Remaing Work
2) Lagging Tasks This Week vs. Last Week
3) Upcoming Tasks This Week vs. Last Week
reporting. However, they are doing this report manually by copying and
pasting from the project plan I send them into an Excel spreadsheet that has
formulas to calculate and get these results. Can you give me some tips on
custom reporting that can be automated in MS Project that would give me these
same results? It seems so manual how they are doing it now and it seems like
there must be a way to have this information in custom reports run directly
from the project plan. They have been doing this for years and no one seems
to use MS Project reports and I think there must be an easier way to automate
this. Thanks.
1) Baseline comparison calculation from Day 1-100 of project
i) 100 Day % Complete
ii) Baseline % Complete today
iii) Actual % complete today
iv) Variance
v) Work last week
vi) Actual Work
vii) Remaing Work
2) Lagging Tasks This Week vs. Last Week
3) Upcoming Tasks This Week vs. Last Week