A
Angela
I have a very large schedule that was originally created in Project 98. I'm
now using 2003 version, and whenever I try to update % complete based on an
older date (in order to get a planned % complete) it moves my dates out as if
it were resource balancing the schedule.
Help,
Angela
now using 2003 version, and whenever I try to update % complete based on an
older date (in order to get a planned % complete) it moves my dates out as if
it were resource balancing the schedule.
Help,
Angela