I was wondering if there is a way to determine which tasks are tracking late
against their % completes. As far as I can see, Project tracks late tasks
against the baseline. What about tracking a task against a manually entered
% complete. Lets say there is a 10 day task with 5 days remaining. It
should be 50% complete, but was only entered at 40% complete. Is there a way
to filter out these tasks that are behind?
Thanks for the help,
Brian Ditman