I had already done that, and it doesn't achieve what I want it to
achieve. We are doing the external decorations of 1500 properties.
During the winter months (Dec, Jan, Feb), we do not do any external
decorations. I have set these as non-working time (logically, it
would just be for the tasks, but I've also tried changing the
resource calenders too).
The external decs take 3 days. Currently, some of the properties are
set to start a day or two before the 3 month layoff (I used levelling
to schedule the properties into sequence). This means that it appears
to take 3 months to complete 1 property. Obviously, we would be quite
happy for those properties to be completed in the first couple of
days of the layoff, and we know that is what would happen. However,
our client, on seeing the project, would recognise this as a flaw in
our plan.
I need a way to ensure all work is completed in one continuous block,
with no non-working time in between. If a task will not be finished
before the start of non-working time, it should not be started at all
(imaging Mrs Jones having a half painted house for 3 months).
Ideas?
Thanks
Dave
Akram Hussein said:
Hi,
time can be defined by going to Tools / Change Working time then
you select the days that you need to be marked as non-working.
Furthermore you must ensure that all resources are using the same
calendar and their non working time is same as of the project.
If you are using MS Project Server then you will be probably need to
do this in the enterprise global template and it will reflect in all
projects. --
Akram Hussein [Microsoft Office Project MVP]
David M C said:
How can I ensure that any given task does not go through
non-working time? For instance, a 4-day task should only start on
Monday or Tuesday such that it is not WIP during the weekend?
Thanks
Dave