Drag an end date an all tasks follow...

S

Sally in Toronto

Hi all,

How can I link a group of tasks together such that when an end date is
modified all the tasks move with the modified end date, keeping the defined
lag times?

i.e. I have a range of tasks related to when my company will relocate. The
date of this move keeps changing. As the move date is modified I want all
the associated tasks to automatically move with the end date.

Thanks,

Sally.
 
M

Mike Glen

Hi Sally,

Welcome to this Microsoft Project newsgroup :)

You shouldn't need to adjust the Dates of subsequent tasks
unless you've entered dates in the Start or Finish fields, as these will
thus have constraints. Without constraints, the successor tasks will
automatically adjust in accordance with their precedence links.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
S

Sally in Toronto

Thank you Mike,

I think a better way to describe my challenge is that when a 'successor"
moves I want the "predecessors" to follow. Not the other way round as you
describe.
 
M

Mike Glen

Well, Sally, there's no special in-built way to do this other than for the
whole project. The only workaround I can think of at the moment is to
create a new milestone to mark the begining of the group of tasks. Then
link FS to every starting task in the group. Then "fix" the milestone by
typing in its Start date. Then, subsequently, if you want a future
milestone date to change, just change the Start date of the new milestone
and it will push the subsequent tasks to the date you want those to start.
In project, you can only push subsequent tasks to a later date using the
Precedence links.


Mike Glen
Project MVP
 
J

Jan De Messemaeker

Hi Sally,

Wouldn't we all!
What you're looking for is called "just in time" and Project doesn't have
that feature, sorry :-(
 
S

Sally in Toronto

"Thanks" everyone.

Mike Glen said:
Well, Sally, there's no special in-built way to do this other than for the
whole project. The only workaround I can think of at the moment is to
create a new milestone to mark the begining of the group of tasks. Then
link FS to every starting task in the group. Then "fix" the milestone by
typing in its Start date. Then, subsequently, if you want a future
milestone date to change, just change the Start date of the new milestone
and it will push the subsequent tasks to the date you want those to start.
In project, you can only push subsequent tasks to a later date using the
Precedence links.


Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top