JimS
For a given task, how do I find the predecessor that most closely binds it to
its current start or finish? I may have a half-dozen predecessors all over
the schedule. I want the one that is pushing out this activity.
its current start or finish? I may have a half-dozen predecessors all over
the schedule. I want the one that is pushing out this activity.