I have a fixed work task. I go to task usage sheet and click on the assign
resources icon. I add a resource at 0% allocation because I want to enter
the monthly hours estimate for this resource. However, project adjusts the
hours for the previously assigned resources. I don't understand why it is
recalculating and changing things when I have only assigned a 0% allocated
resource. There is no work associated with this resource yet.
Can someone please explain?
I am using MSOP 2007.