Hi Andy,
I'm sorry, I have been unable to reproduce the problem. When I create a
project based upon a template, the Gantt chart view opens with the
original template start date. When I go to Project > Project
Information and supply the new project start date, the Gantt chart
automatically adjusts to the new start date. Saving, closing, and
re-opening the new project file opens the Gantt chart view as it was
saved. If I scroll to a new date, save, close, and re-open, the view
opens again, as it was saved.
Try the following:
Open your project
Select the first task in the list and click on the Go to Selected Task
toolbar button on the Standard toolbar to scroll the Gantt Chart bars
into view.
Save the file.
Close the file.
Re-open the file.
Does it open as it was saved, with the bars in view?
I hope this helps. Let us know how you get along.
Julie
AndyB said:
I have exactly the same problem. Project start date is May 06 but the
Gantt
opens at Sept 04. If I click once anywhere on the horizontal scroll
bar
except the arrows it immediately jumps to where it should be. I
thought it
was due to the creation date as mine are templates from before I
joined the
company but that doesn't seem to be the case judging from the file
properties/general tab. There are no tasks or actions of any kind in
2004.
This has also become an excuse for PM's to debunk the use of these
templates
because of what is afterall just a formatting issue. Any help would
be
greatly appreciated.
AndyB.