Hi Pete,
Welcome to this Microsoft Project newsgroup
As I understand it, Project places tasks in the calendar in ID order. If
there are too many to show, Projects lists them in an Overflow list. If you
increase the space available, more items will show and there will be less
overflow. Try moving the cursor on the dividing line between weeks until it
turns into an up/down arrow, click and drag down to increase space until the
Overflow arrow disappears. If that is not enough, try a right-click in the
Calendar and select Layout Now, whence Project will make another attempt to
fit all the tasks in view. Remember that you can always click and drag
tasks upwards to fit into a suitable space. Other than that, you have to
resort to making the font smaller via Format/Text Styles...
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP