Hi All,
Is there a way to hide tasks that don't start before a particular date. I
would like to easily be able to show just those tasks that have either
started or are in progress at a specific point in time.
TIA
George
Is there a way to hide tasks that don't start before a particular date. I
would like to easily be able to show just those tasks that have either
started or are in progress at a specific point in time.
TIA
George