How can I change the days assigned as weekend in Project 2003?

A

AndrewK

Our weekend is not Saturday and Sunday but Friday and Saturday. I would like
to set up a project template which assigns Sunday as a working day and Friday
as a non-working day as a matter of course. Is there a simple way to do this,
please?
 
J

Jan De Messemaeker

Hi,

Yes.
Tools, change working time, Standard calendar (which is the default option)
Select the F header (F for Friday) click nonworking time
Select the S header for the Sundays
Click Nondefault Working Time
Click OK
save the file
Want this for all new files?
Tools, Organizer, Calendars, select Standard in the file, verify Global.mpt
is the other file, click copy.
HTH
 
J

Jan De Messemaeker

Hi,

Yes.
Tools, change working time, Standard calendar (which is the default option)
Select the F header (F for Friday) click nonworking time
Select the S header for the Sundays
Click Nondefault Working Time
Click OK
save the file
Want this for all new files?
Tools, Organizer, Calendars, select Standard in the file, verify Global.mpt
is the other file, click copy.
HTH
 
A

AndrewK

Jan

Brilliant! Just what I wanted to know. Many thanks for your expert assistance.

AndrewK
 