How do I move the start date for all tasks when none are linked?

H

hal_32

I've imported a large number of tasks from Excel. They are not linked. I
need to move all of their start dates by a fixed time. Is there a Project
command or simple macro that can do this?
 
J

Jan De Messemaeker

Hi,

Yes.
Depending on your version:
P98 or P2000: Tools, Macro, Macros, Adjust Dates, Run
Later versions Tools, Customize, Toolbars, Toolbars pad, check Analysis,
click Adjust Dates icon.

HTH
 
G

Gérard Ducouret

Hello HAL,
In the Analysis tool bar of Project 2003, Click the Adjust Dates button.

Gérard Ducouret
 