In Project 2000 how do I change the calendar for dependencies

C

Carl Dube

It appears that task dependencies use the default schedule calendar for
calculating lag dependencies even if I assign a specific task calendar to the
two tasks that are linked. Is there a way to overide this for specific
tasks. I am trying to set dependency lag times in calendar days instead of
working days for some tasks.
 
J

JulieS

Hi Carl,

You can used elapsed time measurements for lag, lead or duration. To use
elapsed time, precede the measurement (days, hours, weeks) with an e. For
example 10eh lag would be 10 hours (on the clock not working time) applied
to the link relationship. One note of caution: an elapsed day is 24 hours,
not the 8 hours that is usually defined as the definition of a day, so a 1ed
lag would be 24 hours later.

Hope this helps. Let us know how you get along.

Julie
 
J

JulieS

Hi Carl,
You are very welcome and thanks for the feedback. Do let us know if we can
assist again in the future.

Julie
 