C
Carl Dube
It appears that task dependencies use the default schedule calendar for
calculating lag dependencies even if I assign a specific task calendar to the
two tasks that are linked. Is there a way to overide this for specific
tasks. I am trying to set dependency lag times in calendar days instead of
working days for some tasks.