D
DT1975
Hi I am a relative newcomer with Project so I apologise if this is a
basic question......
Essentially I have added a new task to a completely fresh project plan.
The task is to start on 4th May 2009 and is to run for 25 days. The
calendar is set up so that the working day is 09:00 to 17:00 and is 7
hours long for 5 days per week. Project is calculating the end date as
Tuesday 2nd June when it should actually be Friday 5th June (25 days
after the start). If I change the end date manually to 5th June it tells
me the duartion is actually 28.43 days and not 25 which doesn't make
sense.
Can anyone advise what I need to do to have the task running for 25
days with an end date of 5th June?
Thanks
basic question......
Essentially I have added a new task to a completely fresh project plan.
The task is to start on 4th May 2009 and is to run for 25 days. The
calendar is set up so that the working day is 09:00 to 17:00 and is 7
hours long for 5 days per week. Project is calculating the end date as
Tuesday 2nd June when it should actually be Friday 5th June (25 days
after the start). If I change the end date manually to 5th June it tells
me the duartion is actually 28.43 days and not 25 which doesn't make
sense.
Can anyone advise what I need to do to have the task running for 25
days with an end date of 5th June?
Thanks