M
Marcos Mello
Hi All
I have a problem with MSP 2000... I'm trying to assign two diferents
calendars in a schedule, but didn't can to schedule resources according the
plan. The second calendar have diferent workload than MSProject, so, the
resource's workload didn't correct... I tryed to change task calendar,
resource calendar, but nothing runs. I dont know what to do now.. please I
need help !!
Thanks in advance
Marcos Mello
Brazil
I have a problem with MSP 2000... I'm trying to assign two diferents
calendars in a schedule, but didn't can to schedule resources according the
plan. The second calendar have diferent workload than MSProject, so, the
resource's workload didn't correct... I tryed to change task calendar,
resource calendar, but nothing runs. I dont know what to do now.. please I
need help !!
Thanks in advance
Marcos Mello
Brazil