M
Mark T
I have multiple resources working/assigned to the same
task. Each resource has a different amount of assigned
(planned) task hours of work effort. I do not want Proj
Pro 2003 to redistribute those planned/remaining hours
differently across those resources,
1. as actuals are posted against the task, and/or
2. the user performs a recalc operation such
as "Reschedule uncompleted work to start xx/xx/xx" under
UpdateProject.
Projects wants to distribute the total task work evenly
between the resources or by their percentage of
utilization.
Basically I want MS Project to work like Niku(ABT)
Workbench does in their Repository system. No I can't
switch products, besides every scheduling tool has it's
issues.
task. Each resource has a different amount of assigned
(planned) task hours of work effort. I do not want Proj
Pro 2003 to redistribute those planned/remaining hours
differently across those resources,
1. as actuals are posted against the task, and/or
2. the user performs a recalc operation such
as "Reschedule uncompleted work to start xx/xx/xx" under
UpdateProject.
Projects wants to distribute the total task work evenly
between the resources or by their percentage of
utilization.
Basically I want MS Project to work like Niku(ABT)
Workbench does in their Repository system. No I can't
switch products, besides every scheduling tool has it's
issues.