Can I highligh a group a tasks to work with one calendar and another group of
tasks to work with a different calendar? Also will the start and finish dates
still affect each other even though some of the tasks use different
calendars?
 
J

Jan De Messemaeker

Hi,

Yes, and Yes.
Select all, right-click, Task information, advanced, calendar.
HTH
 
T

TechArch

Therefore if I have a group of tasks set with one calendar and one of the
tasks has dependency on a task that belongs to another group that is setup
with the other calendar then any change to the dates will roll through both
groups and both calendars?
 
J

Jan De Messemaeker

Hi,

All tasks will be schedules according to their calendar and dependencies
will be respected.
What more can I say?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top