on a split task want to complete early duration stable

J

John M

I split a task and want to post completed task earlier then split end date
keeping the same duration and start date but changing the end date.
 
D

DavidC

Not sure if this is what you are wanting, but here goes. Use the "Update
tasks" button on the tracking toolbar. That allows you to set the start and
end date. That will likely change the duration since if the original end date
was set by the duration, then starting earlier will reduce the duration. It
all depends on how you did the split. I have found that it is possible to
split a task and the duration remains the same if the task is set with a
"Fixed work" task type.

Hope this is of some help.

Regards

DavidC
 
J

John M

David C
I worked out my problem by using the present comlete to avoid either
changing the end date or duration and only accounting for the orginial time
when I created the split. But thank you for the follow-up.