Open resource pool to current date

L

LauraC

How can I setup MS Proj 2000 resource pool to open at the current date. Right
now everytime I open the pool it opens at 2002 the project start date. I have
to scroll over to 2007 each time I open the pool.
 
R

Rod Gill

manually, press F5 or Ctrl+G and enter the date. This will scroll you to the
entered date. Automatically you can add a VBA macro that runs every time you
open the project. The code is:

EditGoto Date:=Date
 