ordering tasks by % completion

B

barry

I would like to order tasks by % completion, from 0% to 100%, across all
tasks. how do i do this?
 
J

Jan De Messemaeker

Hi,

Follow me on the menu:
Project
Sort
Sort By...
select %complete
Down on this form DESELECT Keep outline structure
OK
 